Draft Timeline
Draft Timeline (2010-11) (not yet approved)
2010
June 22 Sections 50% draft complete
Jun 29 Sections 50% draft review (Summer ASHRAE Meeting)
Aug 31 Sections 75% draft complete
Sep 30 100% Draft standard completed
Straightened out. Include appendices. Include definitions.
Sep 30-Oct 1 Interim meeting and 100% draft review
Nov 23 SPC 100 vote to approve standard for public review
Dec 31 Submit draft package to ASHRAE for public review.
2011
Feb 1 Las Vegas ASHRAE Meeting- There will be a main committee meeting, but we may or may not need WG meetings. Would like to present another SPC 100 update seminar.
Feb 15 Last date for SPC 100 draft standard package due to ASHRAE for spring 2011 public review.